THE SISCA ORGANIZATION recently completed the concrete superstructure on a 29 story high rise apartment building in New Rochelle, NY. A typical floor (13,600 sq. ft. / 380 cubic yards of concrete) was being poured in a 4 day cycle, using a concrete telescopic placing boom. The concrete project began in early winter 2020 and was completed by April 2021.